Lagless Status - PDU Maintenance – Maintenance details

All systems operational

PDU Maintenance

Completed
Scheduled for February 05, 2025 at 8:00 PM – 8:36 PMUTC

Affects

Data Centers

Under maintenance from 8:00 PM to 8:36 PM

Dallas Metro

Under maintenance from 8:00 PM to 8:36 PM

DFW1 - Dallas, TX - Equinix DA11

Under maintenance from 8:00 PM to 8:36 PM

Internal Systems

Under maintenance from 8:00 PM to 8:36 PM

Virtual Private Servers

Under maintenance from 8:00 PM to 8:36 PM

Dedicated Servers

Under maintenance from 8:00 PM to 8:36 PM

Updates
  • Completed
    February 05, 2025 at 8:36 PMUTC
    Completed
    February 05, 2025 at 8:36 PMUTC

    We've completed this maintenance early. If you are experiencing any issues, please open a ticket.

  • In progress
    February 05, 2025 at 8:00 PMUTC
    In progress
    February 05, 2025 at 8:00 PMUTC
    Maintenance is now in progress
  • Planned
    February 05, 2025 at 8:00 PMUTC
    Planned
    February 05, 2025 at 8:00 PMUTC

    We will be performing a brief maintenance on our PDUs tomorrow. Client impact is expected to be minimal, as your service may go offline for just a few moments while we swap parts.