Lagless Status - ATL - Upstream Maintenance – Maintenance details

All systems operational

ATL - Upstream Maintenance

Completed
Scheduled for November 16, 2025 at 1:00 AM – 5:00 AMUTC

Affects

Data Centers

Under maintenance from 1:00 AM to 5:00 AM

Atlanta Metro

Under maintenance from 1:00 AM to 5:00 AM

ATL1 - Atlanta, GA - Coresite AT1

Under maintenance from 1:00 AM to 5:00 AM

Internal Systems

Under maintenance from 1:00 AM to 5:00 AM

Game Servers

Under maintenance from 1:00 AM to 5:00 AM

Virtual Private Servers

Under maintenance from 1:00 AM to 5:00 AM

Updates
  • Completed
    November 16, 2025 at 5:00 AMUTC
    Completed
    November 16, 2025 at 5:00 AMUTC
    Maintenance has completed successfully
  • In progress
    November 16, 2025 at 1:00 AMUTC
    In progress
    November 16, 2025 at 1:00 AMUTC
    Maintenance is now in progress
  • Planned
    November 16, 2025 at 1:00 AMUTC
    Planned
    November 16, 2025 at 1:00 AMUTC

    Our upstream provider in Atlanta will be performing planned network maintenance to upgrade their core infrastructure. As part of this work, they are deploying a new Juniper MX304 router.

    This upgrade will increase their backbone capacity to 4.8Tbps and introduces 400G interfaces. These improvements will help strengthen overall performance, stability, and long-term scalability for the region.

    During this maintenance window, our Atlanta services will go offline until the migration to the new router is complete. Their engineering team will work to keep the downtime as short as possible and restore all services quickly.

    We appreciate your patience and understanding while this upstream maintenance is completed. If you have any concerns, feel free to reach out.