Lagless Status - Dallas Datacenter Migration – Maintenance details

All systems operational

Dallas Datacenter Migration

Completed
Scheduled for November 16, 2025 at 6:30 AM – November 19, 2025 at 10:17 PMUTC

Affects

Data Centers

Under maintenance from 6:30 AM to 10:17 PM

Dallas Metro

Under maintenance from 6:30 AM to 10:17 PM

DFW1 - Dallas, TX - Equinix DA11

Under maintenance from 6:30 AM to 10:17 PM

Virtual Private Servers

Under maintenance from 6:30 AM to 10:17 PM

Dedicated Servers

Under maintenance from 6:30 AM to 10:17 PM

Colocation Services

Under maintenance from 6:30 AM to 10:17 PM

Updates
  • Completed
    November 19, 2025 at 10:17 PMUTC
    Completed
    November 19, 2025 at 10:17 PMUTC
    Maintenance has completed successfully.
  • In progress
    November 16, 2025 at 4:46 PMUTC
    In progress
    November 16, 2025 at 4:46 PMUTC

    Maintenance ongoing - sorry.

  • Update
    November 16, 2025 at 4:46 PMUTC
    Update
    November 16, 2025 at 4:46 PMUTC

    Servers have arrived to DA11, and have been wired.

    As of this message, all DA game nodes aside from Belvoir are online.

  • Completed
    November 16, 2025 at 4:46 PMUTC
    Completed
    November 16, 2025 at 4:46 PMUTC
    Maintenance has completed successfully
  • Update
    November 16, 2025 at 12:36 PMUTC
    Update
    November 16, 2025 at 12:36 PMUTC

    Servers are now in transit to DA11.

  • Update
    November 16, 2025 at 10:03 AMUTC
    Update
    November 16, 2025 at 10:03 AMUTC

    We have racked the internal nodes and built the core network. We are returning to Prime Datacenters to go pick up our nodes now.

  • Update
    November 16, 2025 at 6:44 AMUTC
    Update
    November 16, 2025 at 6:44 AMUTC

    Uplinks have been disconnected, and we are starting to move and label servers accordingly.

  • In progress
    November 16, 2025 at 6:30 AMUTC
    In progress
    November 16, 2025 at 6:30 AMUTC
    Maintenance is now in progress
  • Planned
    November 16, 2025 at 6:30 AMUTC
    Planned
    November 16, 2025 at 6:30 AMUTC

    We’ll be moving our Dallas datacenter from Prime Data Centers to Equinix DA11 this weekend. This move is a big step forward for better reliability, network performance, and future expansion.

    Our team will have the new network fully set up ahead of time, and the actual migration will happen overnight between November 15th and 16th, starting around 12:30 AM CDT on the 16th.

    We’re blocking a 12-hour maintenance window for the move. While we’ll do everything we can to shorten downtime, please expect all Dallas services to be affected during that period. We’ll post updates as the migration progresses, and everything will be back online as soon as we’ve verified stability at the new facility.

    Thanks for your patience and support while we make this upgrade happen.