Lagless Status - ATL - Upstream Maintenance – Maintenance details
All systems operational
ATL - Upstream Maintenance
Completed
Scheduled for November 16, 2025 at 1:00 AM – 5:00 AM
Affects
Data Centers
Under maintenance from 1:00 AM to 5:00 AM
Atlanta Metro
Under maintenance from 1:00 AM to 5:00 AM
ATL1 - Atlanta, GA - Coresite AT1
Under maintenance from 1:00 AM to 5:00 AM
Updates
Completed
November 16, 2025 at 5:00 AM
Completed
November 16, 2025 at 5:00 AM
Maintenance has completed successfully
In progress
November 16, 2025 at 1:00 AM
In progress
November 16, 2025 at 1:00 AM
Maintenance is now in progress
Planned
November 16, 2025 at 1:00 AM
Planned
November 16, 2025 at 1:00 AM
Our upstream provider in Atlanta will be performing planned network maintenance to upgrade their core infrastructure. As part of this work, they are deploying a new Juniper MX304 router.
This upgrade will increase their backbone capacity to 4.8Tbps and introduces 400G interfaces. These improvements will help strengthen overall performance, stability, and long-term scalability for the region.
During this maintenance window, our Atlanta services will go offline until the migration to the new router is complete. Their engineering team will work to keep the downtime as short as possible and restore all services quickly.
We appreciate your patience and understanding while this upstream maintenance is completed. If you have any concerns, feel free to reach out.